Northwest in order to close out this project.
<br />
<br />The City has been withholding 5% of the value of completed work, pending completion of the
<br />punch list, verification of all the quantities, and providing all closeout documents. The following
<br />table provides a summary of the total project cost.
<br />
<br />
<br />The construction contract is based on line item bids and as the Project progresses the quantities
<br />could be over or under the estimate. The quantity adjustments resulted in a reduction of
<br />$54,000 to the contract. In the case of this Project, there were several line items that were
<br />under estimated, which resulted in extra cost. Some of those items include:
<br />• Common excavation
<br />• Main Line Dewatering
<br />• Class 5 aggregate base
<br />• Inline CIPP, 15” RCP
<br />In addition some quantities were over estimated resulting in a cost savings. Some of those
<br />items include:
<br />• Service Line Dewatering
<br />• Select Granular Borrow
<br />• 4” Concrete Walk
<br />• Sodding
<br />
<br />There were four change orders to the contract. Change order number 1 was for installing a
<br />temporary bituminous walk at the corner of Groveland and Arden for the winter. Change order
<br />number 2 was for various water main repairs that occurred during the project. Change order
<br />number 3 was for additional sanitary sewer replacement. Change order number 4 was for
<br />additional work required in repair the lift station.
<br />
<br />Final Difference
<br />Design & Inspection
<br /> Design 177,300.00$ 177,382.60$ 82.60$
<br /> Design - Street 133,300.00$
<br /> Design - Lift Station 44,000.00$
<br /> Bidding 6,000.00$ 5,450.00$ (550.00)$
<br /> Construction 236,000.00$ 261,719.47$ 25,719.47$
<br /> Construction - Street 210,000.00$
<br /> Construction - Lift Station 26,000.00$
<br /> Geotechnical Testing 53,783.00$ 38,954.00$ (14,829.00)$
<br /> MSA Testing 1,000.00$ 2,230.25$ 1,230.25$
<br />Subtotal Design 474,083.00$ 485,736.32$ 11,653.32$
<br />Construction
<br /> Construction 3,186,557.69$ 3,132,718.42$ (53,839.27)$
<br /> Contingency (3%)95,596.00$ (95,596.00)$
<br /> Change Order 1 - Temp. Bit Walk 18,378.76$ 18,378.76$
<br /> Change Order 2 - Water Main Repairs 18,012.48$ 18,012.48$
<br /> Change Order 3 - Sanitary Replacement 36,731.15$ 36,731.15$
<br /> Change Order 4 - Additional Lift Station Work 25,230.98$ 25,230.98$
<br />Subtotal Construction 3,282,153.69$ 3,231,071.79$ (51,081.90)$
<br />TOTAL PROJECT COST 3,756,236.69$ 3,716,808.11$ (39,428.58)$
<br />TOTAL PROJECT COST
<br />Bid/Estimate
|