Extension of Bids 0
<br /> WSB Project., Pahl Avenue Pond Construction
<br /> Project Location: City of St.Anthony,Hennepin County,Minnesota Checked By.N.Marshall
<br /> Project Nos: WSB Project No.1065-271 Date: 07/17/00
<br /> 1 Denotes corrected figure
<br /> Low Bidder 5th Low Bidder 6th Low Bidder 7th Low Bidder
<br /> Base Bid $55,982.00 $66,673.00 $75,524.00 $117,700.00
<br /> Base Bid+Alternate No.1 $79,782.00 $97,633.00 $101,524.00 $177,700.00
<br /> G L Contracting Inc Don Zappa&Son Inc Rybak Exc&Contracting Jay Bros Inc
<br /> Line Item Estimated Unit Estimated Unit Unit Unit
<br /> No. Number Description Unit Quantity Price Cost Price Cost Price Cost Price Cost
<br /> Surface Improvements-Base Bid
<br /> 1 2021.501 Mobilization(2%Max) Lump Sum 1.00 $1,200.00 $1,200.00 $1,300.00 $1,300.00 $1,500.00 $1,500.00 $2,360.00 $2,360.00
<br /> 2 2101.502 Clear Trees Each 12.00 $100.00 $1,200.00 $180.00 $2,160.00 $125.00 $1,500.00 $300.00 $3,600.00
<br /> 3 2101.507 Grub Trees Each 12.00 $100.00 $1,200.00 $180.00 $2,160.00 $120.00 $1,440.00 $300.00 $3,600.00
<br /> 4 2503.541 15"RC Pipe Design 3006 Class V LF 42.00 $52.00 $2,184.00 $40.00 $1,680.00 $40.00 $1,680.00 $50.00 $2,100.00
<br /> 5 2506.602 Furnish&Install 15"RCP Apron w/Trash Guard Each 2.00 $1,500.00 $3,000.00 $925.00 $1,850.00 $1,500.00 $3,000.00 $675.00 $1,350.00
<br /> 6 DIV 2 Foundation Removal and Site Clearance Each 4.00 $750.00 $3,000.00 $2,166.00 $8,664.00 $1,250.00 $5,000.00 $11,500.00 $46,000.00
<br /> 7 DIV 2 Disconnect and Remove Utilities Each 4.00 $1,850.00 $7,400.00 $600.00 $2,400.00 $500.00 $2,000.00 $2,700.00 $10,800.00
<br /> 8 DIV 2 Pond Excavation CY 4,700.00 1 $7.59 $35,673.00 $8.15 $38,305.00 $12.32 $57,904.00 $9.95 $46,765.00
<br /> 9 DIV 2 Seeding(Incl.Topsoil,Mulch&Fertilizer) Acre 0.75 $1,500.00 $1,125.00 $10,872.00 $8,154.00 $2,000.00 $1,500.00 $1,500.00 $1,125.00
<br /> Total Base Bid $55,982.00 $66,673.00 $75,524.00 $117,700.00
<br /> G L Contracting Inc Don Zappa&Son Inc Rybak Exc&Contracting Jay Bros Inc
<br /> Line Item Estimated Unit Estimated Unit Unit Unit
<br /> No. Number Description Unit Quantity Price Cost Price Cost Price Cost Price Cost
<br /> Alternate No.1 -Demolition of Building
<br /> 10 DIV 2 1 Building Demolition Each 4.00 $5,950.00 $23.800.001 $7,740.00 $30,960.00 $6,500.00 $26,000.00 .$15,000.00 $60,000.00
<br /> Total Alternate No.1 $23,800.00 $30,960.0011 $26,000.00 $60,000.00
<br /> Total Base Bid+Alternate No.1 JE $79,782.00 $97,633.00 $101,524.00 $177,700.00
<br /> F:\Wpwin\1065-27\Excel\Bidtab.xis Page 2 of 3
<br />
|