6. Project Schedule <br /> The proposed schedule for this improvement project is as follows: <br /> Task Completion Date <br /> ' 1. Order Feasibili ty Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . March 23, 1 <br /> 999 <br /> ' 2. Accept Feasibility Report and order plans and specifications . . . June 22, 1999 <br /> 3.' Hold public/neighborhood hearing . . . . . . . . . . . . . . . . . . . . . . . . July 27, 1999 <br /> 4. Submit plans for State Aid Review and cost participation September 1, 1999 <br /> ' 5. Approve plans and specifications and order <br /> Advertisement for Bids . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . October 26, 1999 <br /> f6. Receive bids . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . December 2, 1999 <br /> ' 7. Neighborhood Project Initiation Meeting . . . . . . . . . . . . . . . . . . . . April 1, 2000 <br /> 8. Begin construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . May, 2000 <br /> 9. Substantial completion of construction . . . . . . . . . . . . . . . . . . . . . August, 2000 <br /> 10. Final completion of construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . July, 2001 <br /> ' City of St.Anthony A <br /> 2000 Street&Utility Improvement Project WSB <br /> Feasibility Report <br /> e nn�an.rK. <br /> WSS Project No. 1065.25 <br /> Page 10 <br />